Because the site has many internal components that must inter-operate correctly for the site to function, and also due to the traffic load, the site must be carefully updated in a coordinated way. We have developed a weekly release schedule with different stages for development, localization, and QA, which you can read about below.
Release Schedule
All times in Pacific Time (GMT-8 or GMT-7, depending on daylight savings).
The release schedule repeats these stages weekly:
- Development
- Beginning with the Tuesday morning push, the source tree is re-opened for changes. Approved patches (changes) may be committed until the tree closes on Thursday night.
- String Freeze
- At the end of Thursday the source tree enters a string freeze. This means that no changes are allowed which would modify or add strings marked for localization. This allows our translators 3 full days (including the weekend) to work on translations. Exceptions to the string freeze are at the discretion of the module owner, but generally not granted.
- Full Freeze
- On Sunday night the source tree is locked down, and no changes are allowed. This gives us one day where we can QA the site before releasing it to production on Tuesday morning