* All work will be done on branch of CC code repository, against existing theme to minimize integration time and regressions
 
* All work will be done on branch of CC code repository, against existing theme to minimize integration time and regressions
  
== Roadmap ==
+
=== Helping ===
  
* note: each deadline below assumes CC approval on same date, given constant communication during development; Check-in on progress each day via skype/IRC
+
* [http://code.creativecommons.org/issues Features and Issues]
 +
* [[Website_update_2011/HOWTO_Update_Website_Front_Page]]
 +
* [[Website update 2011 Past Notes]]
  
=== Implement "phase 1" redesign for main CC website ===
+
[[Category:Development]] [[Category:Website]] [[Category:2011]]
* 8/22 identify concrete elements of "phase 1" mockup design to be implemented, any elements not feasible that will not be implemented
 
* 8/26 home page and navigation elements implemented; check-in with CC web redesign committee
 
* 9/2 changes to interior landing and about themes/pages implemented
 
* 9/9 overall look/navigation changes also implemented for license chooser; check-in with CC web redesign committee
 
* 9/16 bug fixing/testing  completed, launch at CC global summit
 
 
 
=== Post-summit redesign of CC net/donor site ===
 
* 10/7 integration of design elements from main website redesign completed for pre-testing of campaign soft launch
 
 
 
=== Post-campaign launch redesign of other sites ===
 
* goal for each is to incorporate key elements from redesign, but start from and stay very close to native theme of relevant software
 
* 10/14 wiki
 
* 10/21 labs/other CC sites using wordpress multiuser
 
* 10/28 search
 
* cc.net?
 

Latest revision as of 07:06, 11 October 2011

Overview

  • CC is working on a website redesign; primary visual redesign to be completed by CC Global Summit (16 September 2011)
  • initial mockups provided by Lybba Dec 2010
  • design work will be continued by Fabricatorz Aug 2011; primary contacts Jon Phillips, Christoper Adams
  • CC manager Mike Linksvayer; help from CC Tech (Nathan Kinkade, Christopher Webber), Jane Park, Timothy Vollmer
  • All work will be done on branch of CC code repository, against existing theme to minimize integration time and regressions